CPA Projects – Detailed Report


Project Information
Tashmoo Spring Building preservation
Tisbury
33787
296
Continuing rehabilitation, preservation and restoration including brickwork, coal bunker area, and other exterior items
Project complete
04-10-2012
Project Category
      Yes  
Project Details
Housing Units
0
0
0
Acres
0
0
0
0
 
0
0
CPA Funding
$45,000
$0
$0
$0
$0
$45,000
$0
0
 
$0
Other Funding Sources Leveraged
$0
$0
$0
$0
$0
Total Project Cost
$45,000