CPA Projects – Detailed Report


Project Information
Allen Street Mixed Use Renovation
Somerville
43139
274
Schematic design to rebuild the Allen Street Open Space. The design will seek to maintain or expand the 16 existing community garden plots and benches for neighbors. It will also add a play area for children, serving the surrounding community and the Allen Street Head Start School, which is directly across from the open space.
Project complete
04-28-2016
Project Category
    Yes    
Project Details
Housing Units
0
0
0
Acres
0
0
0
0
 
0
0
CPA Funding
$0
$0
$20,000
$0
$0
$20,000
$0
0
 
$0
Other Funding Sources Leveraged
$0
$0
$0
$0
$0
Total Project Cost
$20,000
$0