CPA Projects – Detailed Report


Project Information
FIRST CHURCH BELL & CLOCK TOWER
Wenham
43454
320
RENOVATION WORK TO BELL & CLOCK TOWER. Original project appropriation was for $64,100 for the bell and clock tower, but after negotiations for the grant agreement and preservation restriction, the project scope was reduced to just the clock repairs at the value of $14,100. Work was completed by the First Church and the project was closed out.
Project complete
04-02-2016
Project Category
      Yes  
Project Details
Housing Units
0
0
0
Acres
0
0
0
0
 
0
0
CPA Funding
$0
$0
$0
$14,100
$0
$14,100
$0
0
 
$0
Other Funding Sources Leveraged
$0
$0
$0
$0
$0
Total Project Cost
$14,100
$0
Show fields from Show fields from Show fields from a related table