CPA Projects – Detailed Report


Project Information
Bagg Brook Heritage Landscape Poject
West Springfield
45144
325
Funds for this project will be used to construct 3/4's of a mile of accessible interpretive trail, construct a new entrance, provide dedicated parking, restore and create wetlands and improved drainage using low impact development techniques. This will take place on the original 20.72 acre former Elks property.
Project complete
06-19-2021
Project Category
Yes        
Project Details
Housing Units
0
0
0
Acres
0
0
0
0
 
0
0
CPA Funding
$184,812
$0
$0
$0
$0
$184,812
$0
0
 
$0
Other Funding Sources Leveraged
$0
$0
$0
$184,188
$0
Total Project Cost
$369,000
$184,188