CPA Projects – Detailed Report


Project Information
85D - Invasives Control - Lathrop Communities
Northampton
49506
214
continued priority invasive species removal at Lathrop Community's North and East campuses
Project in progress
03-19-2020
Project Category
Yes        
Project Details
Housing Units
0
0
0
Acres
0
0
0
0
 
0
0
CPA Funding
$3,000
$0
$0
$0
$0
$3,000
$0
0
 
$0
Other Funding Sources Leveraged
$0
$3,000
$0
$0
$0
Total Project Cost
$6,000
$3000