CPA Projects – Detailed Report


Project Information
Yapp Farm Parking Lot
Dracut
51777
79
With the acquisition of the former Yapp farm site, consisting of 28+ acres, the Open Space Committee and the CPC want to provide parking so that town volunteers can construct trails for the residents to enjoy. The Dracut Engineering Dept is designing the parking lot, wetlands have been flagged and the DPW and/or general contractors may complete the work on the site. about 5-6 parking spaces are anticipated.
Project complete
06-07-2019
Project Category
    Yes    
Project Details
Housing Units
0
0
0
Acres
0
0
0
0
 
0
0
CPA Funding
$0
$0
$50,000
$0
$0
$50,000
$0
0
 
$0
Other Funding Sources Leveraged
$0
$0
$0
$0
$0
Total Project Cost
$50,000
$0