CPA Projects – Detailed Report


Project Information
Robbins Farm Playground, Town of Arlington Recreation Department
Arlington
52053
10
This high-use playground has served as a destination for both residents and non-residents since it was built by volunteers in 2003. Today, the existing structures are beyond their useful life and the existing hill slides have been replaced multiple times and are again out of service. The current conditions present hazards warranting immediate capital investment. And further, there are accessibility issues with the site which could be addressed during a renovation. This renovation will present the community with an ADA-compliant playground that has play structures meeting all of today's highest safety standards, fits into the character of the park, and willbe a source of enjoyment for residents and visitors for years to come.
Project in progress
05-18-2022
Project Category
    Yes    
Project Details
Housing Units
0
0
0
Acres
0
0
0
0
 
0
0
CPA Funding
$0
$0
$997,993
$0
$0
$997,993
$0
0
 
$0
Other Funding Sources Leveraged
$0
$0
$0
$0
$0
Total Project Cost
$997,993
$0