CPA Projects – Detailed Report


Project Information
BROAD STREET STILES/HART
Bridgewater
52649
42
The Stiles & Hart Parkland Improvement Project consists 5 major components 1-improved & added parking 2-new trail layout utilizing existing/add new trails 3-multiple footbridges 4-canoe launch improvement 5-new trailhead locations & interpretive signage. This project will support improvements to the Town River Landing Area, and a grant has been applied for through LWCF to assist with the costs - Grant funding will return back to the CPA funding.
Project in progress
06-21-2022
Project Category
Yes        
Project Details
Housing Units
0
0
0
Acres
0
0
0
0
 
0
0
CPA Funding
$1,300,000
$0
$0
$0
$0
$1,300,000
$0
0
 
$0
Other Funding Sources Leveraged
$0
$0
$0
$0
$0
Total Project Cost
$1,300,000
$0
Show fields from Show fields from Show fields from a related table