CPA Projects – Detailed Report


Project Information
Old Town Hall improvements
Somerset
53038
273
Restoration of the entrance to include construction of an accessible entrance, improvements to the parking with a new handicapped parking configuration, replacement of the existing accessible entrance on the south side of the building, replacement of the ramp and other modifications to be determined during the design of the project, including but not limited to site preparation, equipment, furnishings and any other incidental and related costs
Project in progress
05-16-2022
Project Category
      Yes  
Project Details
Housing Units
0
0
0
Acres
0
0
0
0
 
0
0
CPA Funding
$0
$0
$0
$125,000
$0
$125,000
$0
0
 
$0
Other Funding Sources Leveraged
$0
$0
$0
$0
$0
Total Project Cost
$125,000