CPA Projects – Detailed Report


Project Information
Stone dust path
Bedford
625
23
To enable the DPW to improve the accessibility of 5,000 feet of  town trails by installing a 5 foot wide stone dust path.
Project complete
03-24-2004
Project Category
    Yes    
Project Details
Housing Units
0
0
0
Acres
0
0
0
0
 
0
0
CPA Funding
$0
$0
$32,417
$0
$0
$32,417
$0
0
 
$0
Other Funding Sources Leveraged
$0
$0
$0
$0
$0
Total Project Cost
$32,417